B. The Supplier
C. Both
D. Neither
' S: D Y7 r( V) X
77. If procurementor contracting is to be undertaken during the early stages of the project,which option may need changes once these stages have been completed? C
A. Customer QualityExpectations
B. Change Controland Configuration Management
C. The ProjectBoard and other parts of the project management team
D. Work Packagesand Checkpoint reports
78. Which part ofthe organisation structure negotiates a solution to any problems between theproject and external bodies? B
A. Project Manager
B. Project Board
C. Corporate orprogramme management
D. Team Manager
$ E) t4 G* c- N8 J/ Y3 g) n
79. Who isresponsible for approving the Project Product Description? D
A. Project Manager
B. Senior Supplier
C. Executive
D. All member ofthe Project Board
80. To which rolecan the Executive delegate responsibility for monitoring the Business Case? C
A. Project Manager
B. Senior User
C. ProjectAssurance
D. Project Support
6 u6 d6 a, n9 {1 ` x3 _% x' ~$ y
81. The role of theProject Board is best described as: B
A. Advisory
B. Decision-making
C. Platform fordiscussion
D. Support platformfor the Project Manager
82. A Project Boardconsists of: C
A. Three people;the Executive, the Senior User and the Senior Supplier
B. Four roles; theProject Manager; the Executive, the Senior User and the Senior Supplier
C. Three roles; theExecutive, the Senior User and the Senior Supplier
D. The ProjectManager, the Executive, the Senior User, the Senior Supplier and ProjectAssurance
83. All members ofthe Project Board have responsibilities for: B
A. Selecting theProject Manager
B. ProjectAssurance
C. Writing Product Descriptions
D. Agreeing thebusiness case
84. Which plan issuggested by PRINCE 2 will be used after the project has been closed down? D
A. Project Plan
B. Stage Plan
C. Team Plan
D. Benefits ReviewPlan
9 v1 C0 ?* g" m' C+ Y$ p
85. What are thethree basic levels of plan proposed by PRINCE 2? A
A. Project, Stage andTeam
B. Programme,Project and Stage
C. Stage, Team andException
D. Project , Teamand Exception
3 e" s9 ?+ @0 R# G+ y3 E+ P
86. Which plan is aPRINCE 2 project provides the Business Case with time and cost information? C
A. Project andException Plans
B. Project, Stage,Team and Exception Plans
C. Project Plan
D. Project andStage Plans
87. In a PRINCE 2project the Team Plan is produced by which role? C
A. Project Board
B. Project Manager
C. Team Manager
D. ProjectAssurance ITSS
88. Which of thefollowing is NOT used to update the Project Plan at the end of each stage? B
A. Progress alreadymade
B. Benefits alreadyachieved
C. Any agreedchanges in circumstances
D. Any revisedforecast of cost
1 ?1 A$ l- `' U/ e2 R/ J. M; [
89. When is theProject Plan baselined? B
A. Only when theProject Initiation Document is accepted.
B. Every time theProject Initiation Documents is approved and baselined
C. Only as part ofthe End Project Report
D. All of the above
90. What is updatedat the end of every stage to reflect progress already made, any agreed changesin circumstances, any revised forecast of cost and duration? A
A. The Project Plan
B. The BusinessCase
C. The Risk Log
D. The Stage Plan