【考题训练第十六期】The objective of the Change MP is BEST described as ?

The objective of the Change Management process is most accurately described as?
a) Ensuring that all Changes are recorded, managed, tested and implemented in
a controlled manner
b) Ensuring that Changes to IT infrastructure are managed efficiently and
effectively
c) Ensuring that all Changes have appropriate back-out plans in the event of
failure
d) Protecting services by not allowing Changes to be made

答案是哪个,大家帮忙分析下~

6-石家庄-在路上 发表于 2011-5-31 17:10:40

A

freedom 发表于 2011-5-31 17:28:24

A吧

先锋小编 发表于 2011-5-31 17:29:39

答案:a

xlpxlpxlp 发表于 2011-5-31 17:30:59

本帖最后由 xlpxlpxlp 于 2011-5-31 17:36 编辑

A
SO 78页描述如下:
The objective of the Change Management process is to ensure that changes are
recorded and then evaluated, authorized, prioritized, planned, tested,
implemented, documented and reviewed in a controlled manner.
对B的解释可在81页找到:
Change Management is not viewed as bureaucratic, but is instead the only safety
net preventing them from becoming a low-performer. In other words, IT
management owns the controls to achieve its own business objectives, efficiently
and effectively.