Prince2认证题库连载(三)

61. Which member ofthe Project Management Team is responsible for the Business Case? AA. The ExecutiveB. The Senior UserC. The SeniorSupplierD. The ProjectManager62. Who decides onthe use of the Project Assurance role? CA. ProgrammeManagementB. The ProjectManagerC. The ProjectBoardD. QualityAssurance63. If the projectneeds staff to handle configuration management, they would be part of whichgroup? BA. ProjectAssuranceB. Project SupportC. Specialist TeamD. ProgrammeDirectorate64. If the Projectneeds a configuration librarian, this role would be part of which group? CA. ProjectAssuranceB. Specialist TeamC. Project SupportD. ProgrameDirectorate65. Which part ofthe project organisation assists the Project Manager in handling configurationmanagement? BA. ProjectAssuranceB. Project SupportC. Specialist TeamD. ProgrammeDirectorate
66. If the Projectneeds staff to handle the use of specific planning and control software, theywould be part of which group? DA. ProjectAssuranceB. ProgrammeDirectorateC. Specialist TeamD. Project Support
67. PRINCE 2assumes that the Project Manager normally comes from: AA. The CustomerB. The SupplierC. An independentconsultancyD. The ProjectSupport Office5 ?5 Z5 `) P" J5 l1 z3 }
68. Whoseresponsibility is it to set the overall tolerance levels for the Project? DA. The ProjectManagerB. The ProjectBoardC. The ExecutiveD. Corporate orprogramme management$ p$ j/ Z- C) a: E3 l/ J8 k
69. Whose specificresponsibility is it to ensure that the desired outcome of the project isspecified? BA. The ExecutiveB. The Senor UserC. The ProjectManagerD. The SeniorSupplier& B! u( N8 \8 k/ pe+ ?
70. Who isresponsible for leading and motivating the project management team? BA. The ExecutiveB. The ProjectManagerC. The Senior UserD. The entireProject Board" T5 L( i9 k7 F. n7 V
71. The ProjectBoard has authority and responsibility for the project within the instructionsinitially contained within…? BA. The ExceptionReportB. The projectmandateC. The Risk LogD. The End ProjectReport) F" I/ Q- t( T( i$ w
72. Which phraseapplies to the User representative in a PRINCE 2 project management team? AA. They represent theinterests of those who will use theproject’s productsB. May need to useboth in-house and external teams to construct the final outcomeC. Representationfrom the business viewpointD. Will provide thefunding73. Whose responsibilityis it to ensure effective communication with external stakeholder? BA. Project ManagerB. Project BoardC. ProjectAssuranceD. The Supplier74. Who is ultimatelyresponsible for Project Assurance? AA. The ProjectBoardB. The ProjectManagerC. The QualityAssurance departmentD. The ProjectSupport Office75. Which of thefollowing is true of Quality Assurance? BA. It is the sameas Project AssuranceB. It isindependent of the projectC. It is part ofthe project management teamD. all the above76. In aCustomer/Supplier environment, which party would need a Business Case? CA. The CustomerB. The SupplierC. BothD. Neither' S: DY7 r( V) X
77. If procurementor contracting is to be undertaken during the early stages of the project,which option may need changes once these stages have been completed? CA. Customer QualityExpectationsB. Change Controland Configuration ManagementC. The ProjectBoard and other parts of the project management teamD. Work Packagesand Checkpoint reports
78. Which part ofthe organisation structure negotiates a solution to any problems between theproject and external bodies? BA. Project ManagerB. Project BoardC. Corporate orprogramme managementD. Team Manager$ E) t4 G* c- N8 J/ Y3 g) n
79. Who isresponsible for approving the Project Product Description? DA. Project ManagerB. Senior SupplierC. ExecutiveD. All member ofthe Project Board
80. To which rolecan the Executive delegate responsibility for monitoring the Business Case? CA. Project ManagerB. Senior UserC. ProjectAssuranceD. Project Support6 u6 d6 a, n9 {1 `x3 _% x' ~$ y
81. The role of theProject Board is best described as: BA. AdvisoryB. Decision-makingC. Platform fordiscussionD. Support platformfor the Project Manager
82. A Project Boardconsists of: CA. Three people;the Executive, the Senior User and the Senior SupplierB. Four roles; theProject Manager; the Executive, the Senior User and the Senior SupplierC. Three roles; theExecutive, the Senior User and the Senior SupplierD. The ProjectManager, the Executive, the Senior User, the Senior Supplier and ProjectAssurance
83. All members ofthe Project Board have responsibilities for: BA. Selecting theProject ManagerB. ProjectAssuranceC. Writing Product DescriptionsD. Agreeing thebusiness case
84. Which plan issuggested by PRINCE 2 will be used after the project has been closed down? DA. Project PlanB. Stage PlanC. Team PlanD. Benefits ReviewPlan9 v1 C0 ?* g" m' C+ Y$ p
85. What are thethree basic levels of plan proposed by PRINCE 2? AA. Project, Stage andTeamB. Programme,Project and StageC. Stage, Team andExceptionD. Project , Teamand Exception3 e" s9 ?+ @0 R# G+ y3 E+ P
86. Which plan is aPRINCE 2 project provides the Business Case with time and cost information? CA. Project andException PlansB. Project, Stage,Team and Exception PlansC. Project PlanD. Project andStage Plans
87. In a PRINCE 2project the Team Plan is produced by which role? CA. Project BoardB. Project ManagerC. Team ManagerD. ProjectAssurance ITSS
88. Which of thefollowing is NOT used to update the Project Plan at the end of each stage? BA. Progress alreadymadeB. Benefits alreadyachievedC. Any agreedchanges in circumstancesD. Any revisedforecast of cost1 ?1 A$ l- `' U/ e2 R/ J. M; [
89. When is theProject Plan baselined? BA. Only when theProject Initiation Document is accepted.B. Every time theProject Initiation Documents is approved and baselinedC. Only as part ofthe End Project ReportD. All of the above
90. What is updatedat the end of every stage to reflect progress already made, any agreed changesin circumstances, any revised forecast of cost and duration? AA. The Project PlanB. The BusinessCaseC. The Risk LogD. The Stage Plan+ M& K8 E0 i' s

, S, h& }3 n$ _9 b. d; ~2 G

東東 发表于 2020-11-25 08:33:13

:(
页: [1]